IMPORTANT NOTICE - ONGOING CONSTRUCTION ACTIVITIES



SR 90/US 41/SW 8 Street Avenue from SW 74 Court to SR 9/SW 27 Avenue

Click here to view a project video

Haga clic aquí para ver un video del proyecto

 
 
ONGOING CONSTRUCTION ACTIVITIES
 
Monday, May 22 through Monday, May 29, 2023
Sidewalk, curb ramp and underground electrical work
 
·     Sidewalk and pedestrian curb ramp replacement is underway between Sylvania Blvd and SW 58 Ave
·     Underground electrical work is being performed for traffic signals at various intersections along SW 8 St including:
·     Genoa St, SW 51 Ct and SW 51 Ave
·     Installation of signage bases and signs along SW 8 St is currently underway
 
Lane Closures 
 
·     Temporary lane closures along SW 8 St can occur during non-peak hours on non-event days, nights and weekends from: 
 
·     10 a.m. to 3 p.m., weekdays
·     9 p.m. to 5:30 a.m., Sunday through Thursday
·     11 p.m. to 7 a.m., Friday and Saturday
·     8 a.m. to 6 p.m., Saturday and Sunday 
·     There will be no work activities or temporary lane closures from Saturday, May 27 through Monday, May 29, in observance of Memorial Day.
·     Regular construction activities will resume on Tuesday, May 30.
 
·     Access to and from adjacent neighborhoods and businesses is being maintained during construction
·     Temporary sidewalk detours are in place when necessary
 
 
PLEASE USE CAUTION WHEN TRAVELING THROUGH CONSTRUCTION ZONES, AND NOTE THAT THIS SCHEDULE MAY CHANGE DUE TO BAD WEATHER OR OTHER UNEXPECTED CONDITIONS.
 
For more project information, click here or contact Construction Community Outreach Specialist Jeff Baquedano at (786) 510-6113 or at Jeff.Baquedano@dot.state.fl.us. Drivers are encouraged to log onto www.fl511.com to get real-time traffic and lane closure information.